South Buckhout Street:
As of Thursday, 9/24, the paving on South Buckhout Street is partially complete. The paving crews encountered an area of badly deteriorated roadway that needs to be repaired before paving can be completed. The repairs are being made and paving is expected to resume on Friday morning, 9/25 and be completed by the end of the day. Line striping will take place on Saturday morning while while the cars are off the roadway. Residents can expect parking to become available on South Buckhout Street on a rolling basis through the morning and into the afternoon on Saturday as the painting is completed.
Roads will be accessible to local traffic only. Please use an alternate route. Expect delays.
Hudson View Park:
The paving of the roads in Hudson View Park (Hudson Ave, Park Rd, Center St) are on hold while the contractor waits for some special order materials to arrive. As a result, the start date for paving is unknown at this time.
For any questions or concerns, please call the Department of Public Works at 591-6044.