[ARCHIVED] Updated 2009 Road Resurfacing Schedule

The Village will be resurfacing roads on:
Thursday, September 24, 2009
Friday, September 25, 2009
Monday, September 28, 2009

Updated 2009 Road Resurfacing Project Schedule
(Schedule subject to change in the event of inclement weather)

Thursday, September 24, 2009:

Paving Operations on: Remainder of Riverview Road, Circle Drive and Hermits Road

Friday, September 25, 2009:

Paving Operations on: North Astor Street, South Astor Street, Clinton Avenue, Park Road, Lewis Road and Hamilton Avenue


Monday, September 28, 2009:

Paving Operations on: Osceola Avenue, Field Terrace, Roland Road, Hudson Road East and Langdon Avenue


Any questions, Please contact Greg Nilsson, Superintendent of Public Works.